2021 -2022: Worley/BASF EBMI pCAM Project
Rolle: Electrical Site Supervisor
Kunde: Actemium Large Projects GmbH/Vinci Energies Group
Aufgaben:
- Construction, MC,PC&C activities for electrical equipment's by LV/MV according with planning, coordination, execution and follow up are done in strict compliance with the Detailed Design/specifications and IEEE,ANSI,IEC Standard Codes
- Technical documentation preparation for LV/MV equipment?s
- Normal and Emergency Lighting installations and project site queries-Electrical equipment?s Installation and Inspection in Hazardous Area-testing the LV/MV Bus bars for electrical substations, work plan preparation and supervising in the field the electrical team
2020 - 2021: Tier 1-Data Center Microsoft /Power Plant 4x50 MW
Rolle: SAP Electrical Specialist
Kunde: Dornan Group Ltd.-Data Center Microsoft ?Sweden
Aufgaben:
- MC, Pre-Commissioning, Commissioning Electrical activities for equipment's by LV, MV/HV according with IEEE, ANSI, IEC Standard Codes for Data Center -Microsoft.
- Issued PTW, LOTO system, witness for electrical commissioning activities
- Loop check for emergency generator, U.P.S. & BATTERY ROOM
- Commissioning / supervising and distribution of switchgear and transformers by 11/0.4 KV.
2019 - 2020: Electrical Commissioning Engineering
Rolle: Electrical Commissioning Engineer
Kunde: Steinmueller-Babcock Environment from Germany-EfW Power Plant in Spain
Aufgaben:
- I have managed a team of Supervisors,F/M and Electricians, with day to day activities required to deliver work in line with the project plan including safety, quality, schedule and cost objectives
- worked indoors/outdoors of LV & MV Switchgear Rooms equipped by Siemens, ABB ,Solo Run-in Motors, MCC Inspection/Tests, Installation and test VFD, UPS and BESS Stations by GE from 2-40MW/40MWh and other defined activities according with IEEE,ANSI,IEC Standard Codes
- identify, implement and comply with applicable safety, environmental and quality standards, company procedures and regulatory requirements, anticipate problems by checking in due time planning aspects related to all interfaces issues during Electrical installation/pre-commissioning and commissioning works
further projects on request